An engineer monitors the chain reaction at the Prototype Fast Breeder Reactor core

More than two decades after construction first began, India's Prototype Fast Breeder Reactor (PFBR) at Kalpakkam has achieved first criticality, marking one of the most significant milestones in the country's nuclear energy ambitions, analysed Hugo Rojas on Energies Media.

The 500 MWe reactor attained first criticality at 8:25 pm on 6 April 2026, initiating a controlled and self-sustaining nuclear fission chain reaction. While the control room remained calm, the event represented the culmination of years of engineering, safety reviews and commissioning work.

At the heart of the achievement is a technology that differs fundamentally from most operating nuclear reactors. Instead of water, the PFBR uses approximately 1,750 tons of liquid sodium to transfer heat from the reactor core. This design preserves fast neutrons, which are essential for the reactor's ability to generate more fissile fuel than it consumes.

Unlike conventional reactors that slow neutrons using water, the PFBR relies on fast, unmoderated neutrons to convert non-fissile uranium into plutonium fuel. This breeding process is central to the reactor's strategic importance and explains why liquid sodium was selected despite the engineering challenges associated with handling it.

Liquid sodium remains stable across a wide operating temperature range and transfers heat exceptionally efficiently. However, it reacts vigorously with water, requiring extensive safety measures. To reduce this risk, engineers adopted a pool-type reactor design in which the primary radioactive sodium system remains submerged and isolated from water-bearing systems.

Located at Kokkilamedu near Kalpakkam on Tamil Nadu's coast, adjacent to the Madras Atomic Power Station, the facility is India's first indigenously developed sodium-cooled fast breeder reactor. The site has long served as the focal point of India's fast reactor development efforts.

The reactor employs a two-stage sodium heat-transfer arrangement. Heat from the reactor core is first carried by a primary sodium circuit to intermediate heat exchangers. A separate, non-radioactive secondary sodium circuit then transfers that heat to water, producing steam that drives a turbine-generator capable of generating 500 MWe of electricity. This arrangement prevents radioactive primary sodium from coming into direct contact with steam systems.

The PFBR was designed by the Indira Gandhi Centre for Atomic Research and constructed by Bharatiya Nabhikiya Vidyut Nigam Limited under the Department of Atomic Energy. The reactor uses uranium-plutonium mixed oxide fuel surrounded by a uranium-238 blanket. Fast neutrons convert the uranium-238 into plutonium-239, enabling the reactor to produce more fuel than it consumes.

Officials described the milestone as a major advance for India's long-term energy security. Following the achievement, Prime Minister Narendra Modi stated: “The indigenously designed and built Prototype Fast Breeder Reactor at Kalpakkam has attained criticality,” adding that it “reflects the depth of our scientific capability and the strength of our engineering enterprise.”

The project's path to completion was considerably longer than originally envisaged. Construction commenced in 2004 with an expected completion target of 2010. Regulatory approval for fuel loading and low-power physics experiments was granted in 2024, and full criticality followed only after extensive safety validation and commissioning activities.

Officials have attributed much of the delay to first-of-a-kind technological challenges associated with developing an indigenous fast breeder reactor. Project costs also rose substantially during the extended construction period, increasing to more than double the original estimate.

Despite the breakthrough, commercial operation remains some distance away. Criticality marks the beginning of the operational phase rather than the start of full-scale electricity production. Reactor power will be increased gradually through a series of carefully regulated stages, with extensive testing and verification at each level.

The PFBR also represents a major step in India's three-stage nuclear power strategy, originally conceived to maximise the country's relatively limited uranium resources while ultimately exploiting its vast thorium reserves. With the reactor's entry into service, India formally advances into the second stage of that long-term plan.

The reactor builds upon experience gained from the Fast Breeder Test Reactor, which achieved criticality in 1985 and provided decades of operational knowledge in sodium technology, fuel behaviour and fast reactor physics. The lessons learned there have now been translated into a commercial-scale design.

Once fully operational, the PFBR is expected to place India alongside Russia as one of the very few nations operating a commercial-scale fast breeder reactor. The technology is intended to serve as a bridge towards the eventual large-scale use of thorium-based fuel cycles.

The reactor also incorporates advanced safety systems, high-temperature liquid sodium coolant technology and a closed fuel-cycle approach that allows the recycling of nuclear materials. This improves fuel utilisation and supports long-term sustainability objectives.

Kalpakkam's role extends beyond a single reactor. Plans already exist for additional fast breeder units at the site once the performance of the prototype reactor has been fully validated. The experience gained from the PFBR is expected to shape future commercial reactor designs and support wider deployment of breeder technology across India.

In the longer term, plutonium generated during this second stage of the nuclear strategy will be used to support future breeder reactors and enable the production of uranium-233 from thorium, laying the foundation for the third stage of India's nuclear program.

For now, however, attention remains focused on the careful progression from criticality to full-power operation. The coming months will test systems, pumps, welds, instrumentation and operational procedures before the reactor eventually begins supplying electricity at its rated capacity.

For a project measured in decades rather than years, the quiet achievement of criticality at 8:25 pm was not the conclusion of the story, but the beginning of a new chapter in India's nuclear energy journey.